Here you can find the prioritized list of detailed functionalities, which we plan to implement.

A prioritized list for the implementation of the different environments can be found at the bottom of the page.

The done criteria for the different functionalities are that is installed in the test system and the relevant tests has verified that the feature is working as expected. In case of pillar implementation htis means that a test instance of the pillar is available and used for the acceptance test.

Description

Protocol

Java client

.Net client

Reference pillar

SB tape pillar

SB disk pillar

KB pillar

SA pillar

Connect to message bus

NA

Done

Done

Done

Done

Okt

Done

Done

Send message on message bus

Done

Done

Done

Done

Done

Okt

Done

Done

Send file via. file exchange

Done

Done

Done

Done

Done

Okt

June

Done

Put File

Done

Reviewing

In progress

Reviewing

In progress

Okt

June

In progress

Get File

Done

Done

In progress

Reviewing

In progress

Okt

June

In progress

Get File IDs

Done

In progress

July

In progress

August

Okt

July

July

Get Checksums

Done

In progress

July

In progress

August

Okt

Aug

July

Integrity spike

Done

In progress

NA

In progress

-

-

 

 

Deployable

NA

Aug

 

Jul

August

Okt

 

 

Alarm pilot

Done

Aug

August

Aug

Sep

Okt

Sept

August

Audit trail pilot

Done

Aug

August

Aug

Sep

Okt

Sept

August

Delete File pilot

In progress

Aug

August

Aug

Sep

Okt

Sept

August

Replace File pilot

In progress

Sep

N/A

Sep

Sep

Okt

Sept

 

Get Status pilot

In progress

Sep

August

sep

Sep

Okt

August

August

Protocol versioning

In progress

In progress

July

In progress

Sep

Okt

 

July

Add encryption

In progress

In progress

August

In progress

Sep

Okt

Aug

August

Add authentication

In progress

Sep

August

Sep

Sep

Okt

Aug

August

Consolidate Availability

In progress

In progress

 

In progress

Sep

Okt

 

 

Delete file production

Sep

Sep

Okt

Sep

 

 

 

 

Finish Replace file production

Sep

Sep

N/A

Sep

 

 

 

 

Two phase commit

Sep

Sep

Okt

Sep

Nov

Nov

 

Oct

Integrity production

Oct

Oct

N/A

Oct

-

-

 

 

Audit trail production

Oct

Oct

Nov

Oct

Nov

Nov

 

Nov

Alarm production

Nov

Nov

Nov

Nov

Nov

Nov

 

Nov

Get Status production

In progress

Nov

Nov

Nov

Nov

Nov

Nov

Nov

Checksum pillar

Done

Nov

N/A

Nov

-

-

 

 

Reports

Nov

Nov

 

Nov

Nov

Nov

 

 

Mass Processing spike

Dec

Dec

N/A

Dec

-

Dec

 

N/A

Processing Single File spike

Dec

Dec

N/A

Dec

Dec

Dec

 

N/A

Extend Mass Processing

Dec

Dec

N/A

Dec

-

Dec

 

N/A

Extend Processing Single File

Dec

Dec

N/A

Dec

Dec

Dec

 

N/A

Infrastructure

Prioritized list of the implementation of the different environments needed in the project

Description

Status

Setup test message bus

Done

Setup test file exchange server

Done

Add https to test system

In progress

Setup integration test system

In progress

Setup pilot system

Aug

Setup monitoring component

Sep

Setup production system

Dec

Old versions

As all major updates of the implementation list should been accepted by the project (steering group or the development team), older versions of the plan in made available through the table below. The 'Replacement date' links to the version of the plan used prior to the indicated date.   

Replacement date

Comment

2011-06-17

Startup of plan versioning prior to steering group meeting on the 21th