This is a breakdown of the full project into more manageable milestones

Only the milestones relevant for the development project are liste. The full milestone list can be found here . 

A more detailed breakdown of the task content of the different milestones kan be found in the projects JIRA issue tracker.

milestone timeline

Milestone plan change history

Date

Change

Accepted by steering group

2011.03.22

M4 Development of prototype coordinating layer, client and pillar and [M5 Define system for pilot has been moved to the end of june, as KB feels that the proto type needs to contain much more functionality before we can say that the goal of the prototype has been accomplished, that is a suitable exploration of the protocol and architecture. As a result of this the M6 Develop system for pilot and M7 Pilot in operation have been postpone to september

Agreed in steering group 2011.03.22

2011.03.01

M4 Development of prototype coordinating layer, client and pillar and M5 Define system for pilot has been moved a month back so it now is expected to be finished at the end of march

Pending SC meeting on the 22 march

2010.12.15

Milestone 5 Define pilot system has been moved to the end of February, so it coincides with M4.

2010.12.15.

2010.12.01

The initial goal of finishing milestone 3 at the end of november 2010 has been moved to the 12.jan 2011. We still have many areas of the system which hasn't been specified and are still working on defining the full scope and breakdown of the system. Milestone 5 has been moved 2 weeks to coincide with the milestone 3/iteration 3 finish.

2010.12.15.